Brooklyn Center, MN
Home Menu53rd Avenue Mill & Overlay
Construction is complete with the exception of various punch list items. The contractor is required to provide a warranty on all work for one year from the date of acceptance of the project.
Thanks to all of you for your patience and understanding throughout this process! It is our hope and intent that the improvements, combined with previous, existing, and future improvements throughout the City, will provide a strong and healthy long-term economic base for the entire City and will renew a sense of community and neighborhood pride.
Project Improvements
- Mill and overlay pavement
- New road striping for bike lane
Contact Information
Please contact the project manager for all project coordination issues and information.
Lydia Ener
Assistant City Engineer
763.339.8625 (mobile)
lener@brooklyncentermn.gov
Utility Outages
Please contact the following for utility outages:
- CenterPoint Energy gas leak: (612) 372-5050
- Xcel Energy electric outage: 1 (800) 895-1999
- CenturyLink: 1 (877) 348-9007
- Comcast: 1 (800) 934-6489
- City of Brooklyn Center 7:00 a.m. - 3:30 p.m.: (763) 585-7100
- Water
- Sanitary
- Storm Sewer
- Street Lighting
- Or Traffic Signal Systems
- After hours call 911 (the dispatcher will contact the appropriate on-call service staff)
Project Schedule
- January 2021 - City Council authorized the project and ordered the preparation of plans and specifications
- Summer 2021 - Utility improvement and concrete sidewalk and curb replacements were completed
- January 2022 - City Council to approve mill and overlay plans and specifications and authorize the advertisement for bids
- March 2022 - City Council to accept bids and award contract
- Spring 2022 - Start project construction
Project History
The City of Brooklyn Center’s Capital Improvement Plan identified a potential mill and overlay of 53rd Avenue from Penn Avenue to Lyndale Avenue. This project was scheduled for 2022. A letter was sent out in December of 2021 to inform residents of the project.
On January 24, 2022, the City Council ordered improvements and authorized the preparation of plans and specs for the project.
On March 4, 2022, sealed bids were opened for the 53rd Avenue Mill and Overlay project. The City received numerous bids from qualified contractors. The contract will be awarded at the March 28, 2022 City Council meeting.
At its meeting on March 28, 2022, the City Council awarded the project to GMH Asphalt Corporation of Chaska, Minnesota. Construction is anticipated to start Spring 2022 and will be complete by October 2022. Monthly newsletters and construction updates will be added to this site to give information and reminders about the project.
For a map of the project, please click here.