Home MenuHumboldt Ave Reconstruction – From 53rd Avenue North to 57th Avenue North
Project Updates
The City of Brooklyn Center is preparing for the reconstruction of the Humboldt Ave project area which extends from 53rd Avenue to 57th Avenue.
Project Details
- Full Depth Pavement Replacement with partial curb replacement
- Bituminous trial replacement
- Storm sewer repair
- Water main replacement
- Partial sanitary sewer replacement
Project Schedule
- September 2024: Start Date of Consultant Contract
- February 2026: Anticipated Bid Opening
- April 2026: Start Construction
- November 2026: End Construction
Contact Information
Please contact the City Engineer for all project coordination issues and information:
Ahmed Omer
City Engineer
763.569.3326
Utility Outages
Please contact the following for utility outages:
- CenterPoint Energy gas leak: (612) 372-5050
- Xcel Energy electric outage: 1 (800) 895-4999
- CenturyLink: 1 (800) 954-1211
- Comcast: 1 (800) 934-6489
- City of Brooklyn Center 7:00 a.m. - 3:00 p.m. (763) 585-7100
- After hours call 911 (the dispatcher will contact the appropriate on-call service staff