Project Updates

The City of Brooklyn Center is preparing for the rehabilitation of 67th Ave N from Shingle Creek Parkway to the cul-de-sac, and James Ave N from 67th Ave N to Freeway Blvd. 

On September 23, 2024, the City Council accepted the Feasibility Report and set a date for the Improvement Public Hearing for the project.

The Public Hearing will be held on October 28th, 2024 at 7:00pm as part of the regular City Council meeting, and will give any property owner affected by the improvements an opportunity to address the Council regarding the project. A notice will be sent to property owners prior to meeting with additional information.

Project Details

  • 2-inch bituminous mill and overlay with partial curb replacement
  • Storm manhole casting replacements
  • Sanitary manhole casting replacements
  • Hydrant and gate valve spot replacements

Project Schedule

  • September 2024: Feasibility Report to City Council
  • February 2025: Anticipated Bid Opening
  • May 2025: Start Construction 
  • September 2025: End Construction

Contact Information

Please contact the Assistant City Engineer for all project coordination issues and information:

Lydia Ener
Assistant City Engineer
763.339.8625

Utility Outages

Please contact the following for utility outages:

  • CenterPoint Energy gas leak: (612) 372-5050
  • Xcel Energy electric outage: 1 (800) 895-4999
  • CenturyLink: 1 (800) 954-1211 
  • Comcast: 1 (800) 934-6489
  • City of Brooklyn Center 7:00 a.m.- 3:00 p.m. (763) 585-7100
  • After hours call 911 (the dispatcher will contact the appropriate on-call service staff)